New Project : First Day
Project Background
The Owner (who shall be nameless)
has awarded LSTK contract to build gas storage.
The contractor’s work will be supervised by a PMC (nameless again), who
has also prepared the FEED. The Contractor (of course nameless) has outsourced Detailed
Engineering, because it is not his strength. I will be playing a key role in assisting and
advising the Detailed Engineering Contractor (DEC)
First Meeting
I explained my responsibility and
the authority I need.
The team is yet to be fully
assembled. Piping, Civil and Electrical engineers are on board. Instrument
engineer has been identified. Process engineer’s resume in hand and looks
promising; will interview tomorrow.
We have a copy of the standard to
which the engineering shall mandatorily comply. But it is an older edition. New
version to be procured and made available to all team members.
Tried to work on a list of “milestones”
and the overall schedule, but interrupted by the Contractor, who wanted to meet
urgently. So we dropped everything, grabbed a hasty lunch and went for the
meeting downtown.
Meeting with Contractor
Contractor wants us to take up on
priority 14 documents required for PESO approval. He provided us samples from a
previous project.
Contractor asked us to formally
request for soft copies from FEED, but provided no assurance that PMC will
oblige. If not, we will have to redraw, increasing our effort and chances of
error.
Contractor has not costed for
piling, but it cannot be ruled out. It will depend on soil investigation study
to be undertaken asap. Report will be known in min 4 weeks. Piling will
significantly add to both cost and schedule.
Detailed Engineering will be
impacted by vendor information and we are concerned if Contractor will place
timely orders, though not called for from delivery point of view. Contractor
assuaged our fear , but I am not personally convinced it will happen.
Contractor will provide soft
copies of documents from a similar project to facilitate our work. Sometimes it
is better to start afresh than reuse and own an old document.
Contractor has already prepared a
barricading drawing assuming a layout, which apparently violates PESO guideline. Owner is coaxing him towards this.
Risk Summary
1) Piling?
2) PESO
approval
3) Timely
ordering for vendor information
4) Availability
of FEED Soft Copy.
0 Comments:
Post a Comment
<< Home