Friday, April 14, 2017

Not a Real KOM

PLEASE READ THE EARLIER POST BEFORE YOU CONTINUE FURTHER.
Kick-off Meeting could not be conducted in the true sense because the team was not present in full strength.
Good news: Process Engineer is on board.
Bad news: Instrument Engineer has declined to join. We have to start all over again. Role of Instrument Engineer is very tricky.
Copy of the Engineering Guideline hasn’t been procured yet. We don’t know where to get it from.  Team members have to quickly familiarise with this guideline. They have to demonstrate clause-wise compliance when they submit drawings/documents for my approval.
Reiterated priorities
a)    P&I Ds
b)    Layout
c)    Documents for PESO approval
P&IDs are being redrawn, because FEED documents not up to mark.
Went through the residual engineering activities in detail with the Process Engineer: TSVs, gas detectors, isolation valves, purging connections, drains and vents etc.


It is a brownfield project. The site has to be barricaded from the adjacent live plant before construction can start. There isn’t adequate space for the barricade foundation. Need to think out-of-the box. We aren’t paid for that, so we will only highlight the problem. Important to understand the scope and stay within it. 