Not a Real KOM
PLEASE
READ THE EARLIER POST BEFORE YOU CONTINUE FURTHER.
Kick-off
Meeting could not be conducted in the true sense because the team was not
present in full strength.
Good
news: Process Engineer is on board.
Bad
news: Instrument Engineer has declined to join. We have to start all over
again. Role of Instrument Engineer is very tricky.
Copy
of the Engineering Guideline hasn’t been procured yet. We don’t know where to
get it from. Team members have to
quickly familiarise with this guideline. They have to demonstrate clause-wise
compliance when they submit drawings/documents for my approval.
Reiterated
priorities
a) P&I Ds
b) Layout
c) Documents for PESO approval
P&IDs
are being redrawn, because FEED documents not up to mark.
Went
through the residual engineering activities in detail with the Process
Engineer: TSVs, gas detectors, isolation valves, purging connections, drains
and vents etc.
It
is a brownfield project. The site has to be barricaded from the adjacent live
plant before construction can start. There isn’t adequate space for the
barricade foundation. Need to think out-of-the box. We aren’t paid for that, so
we will only highlight the problem. Important to understand the scope and stay
within it.